Approximately 4.5 miles of 42-inch welded steel potable water pipeline, trenchless crossing of Highway E470, Lincoln Ave, and Meridian Village Pkwy; pipeline appurtenances; flow control structures; new ammonia storage facility, new additional finished water pumps (1) 200HP pump motor and (1) 450hp pump motor in the existing facility, new additions/modifications to the existing IO control system and miscellaneous improvements at the Rueter-Hess Water Purification Facility.
preconstruction & design assist
current
We provide electrical construction solutions that can serve the life of a building with commitment to safe and quality services backed by our strong history of successful projects.