It was determined in a short time that the project would require approximately 1,300,000 man-hours for completion in 12 months on this fast-track project. The Human Resources Department immediately embarked on a nationwide recruitment effort for dedicated, trained and experienced personnel.
Focusing on safety for all resulted in a successful 1,340,000 man-hour project without a lost-time accident.
The 1,757,300 sq. ft. High Tech Campus included:
Manufacturing Building – 728,800 sq. ft.
Class 1 Clean Room – 165,400 sq. ft.
Control Utility building – 26,100 sq. ft.
Process Support Building 82,800 sq. ft.
Test/Lab Building – 265,000 sq. ft.
Warehouse Building – 40,000 sq. ft.
Parking Structure
AGC of Colorado awarded Ludvik Electric a 2001 ACE Award for this project.