The 91st Avenue WWTP is located on 500 acres with a current firm capacity of 204.5mgd.
The UP01 Completion Project consisted of:
Two 84″ interceptors
Influent Junction Structure
Influent Metering and Sampling
Headworks Facility
Screening Building
Grit Collection System and Residual Handling Facility
Two Primary Sedimentation Basins
Primary Sludge Pump Station
Two Aeration Basins
Two IMLR Pump Basins
Dewatering Pump Station
Blower Facility
Chlorination Faciilty
Reuse Water Pump Station
Effluent Conveyance
Two Secondary Sedimentation Basins
RAS/WAS Pump Station
Also included in this project, the construction of an Odor Control Facility, two-stage scrubbers, re-circulatory pumps, scrubber blow down pump station, foul all conveyance system, Chemical Handling Facility, chemical storage, water softener system.
preconstruction & design assist
current
We provide electrical construction solutions that can serve the life of a building with commitment to safe and quality services backed by our strong history of successful projects.